Installation and commissioning of a diesel generator
This article will focus on diesel generators intended for stationary indoor installation. Let's make a reservation right away that it must be well ventilated with the help of windows or openings. The windows at the place of the device are equipped with protection against the penetration of atmospheric precipitation inside and covers for regulating the temperature regime.
Under no circumstances should power plants of this type be placed in rooms with a chemically aggressive environment or high humidity. Their radiator should always face the window, and exhaust gases should be discharged outside the room. The exhaust channel is also protected from atmospheric precipitation. If there is a need for long stops of the device, the path is closed with a special damper or cap. A silencer is installed on the pipeline.
The diesel mini power plant is mounted on a rigid or bolted base. The foundation is a horizontal platform located above the floor at a height of 20-25 cm.A setback of at least one and a half meters from the walls of the building is required. The top of the base is leveled and leveled. In addition, the anchor bolts are cast into the base so that the threaded part protrudes 50 mm above the surface.
The installation of the generator must allow it to be charged and controlled from the side of the shield and radiator. A certain space will also be required to access the diesel generator sets, and this again is at least one and a half meters between the unit and the wall. According to the manufacturer's rules, batteries must be placed in a special box. The room must have all the fire fighting equipment defined by the current rules.
The new generator engine operates at reduced load (no more than 70% of maximum power) during the first hundred hours of operation. Well-executed workmanship allows you to significantly postpone the first repair of the device.
Before starting the commissioning, the diesel generator must be dismantled in accordance with the attached operating instructions. If these actions are not performed, an accident may occur. The following steps: checking all mounting units of the unit, checking its attachment to the frame, tightening the shock absorbers, connecting and securing all piping.
The generator is then filled with filtered fuel of the brand specified in the diesel engine manual and clean oil. The cooling system is full of coolant. After that, the tightness of the pipeline connections and drain valves, the tightness of the clamps and the condition of the connecting hoses made of durite are checked.
The next step is to check the progress of the diesel generator fuel control mechanism and remove the protective seals under the generator ventilation grills. Now you can put in working condition and connect the batteries. Do not start without measuring the insulation resistance of the electrical circuit of the installation and its individual units.
After checking the reliability of the grounding of the power plant, open the valve of the fuel tank, the air release plug of the fine fuel filter and pump the system with a hand pump until a uniform flow of fuel without air bubbles appears from the drain pipe. The plug is then closed and the generator is started.